电动汽车充电桩安装第一步:充电条件确认
Electric vehicle charging pile installation step 1: charging condition confirmation
电动汽车充电桩安装过程中最为关键的一步是充电条件的确认,关键点在于是否有固定停车位和物业同意安装充电桩的申请,搞定这两点你几乎就可以高枕无忧了。那么充电条件的确认具体步骤都有哪些呢?
Electric vehicle charging is the key step is to confirm the charging conditions of pile in the installation process, the key point is that whether there is a fixed parking spaces and the property agreed to install charging pile application, fix these two things and you can almost sleep without any anxiety. Then what are the specific steps to confirm the charging conditions?
电动汽车充电桩安装指南
Guide for installation of electric vehicle charging piles
1、用户与汽车厂商或4S店签订购车意向协议后,办理购车充电条件确认手续,此时需要提供的材料包括:
1, users and car manufacturers or 4S shop signed a car purchase agreement, the purchase of car charging conditions confirmation procedures, at this time the required materials include:
1)购车意向协议;
1) car purchase intention agreement;
2)申请人身份证明;
2) identity certificate of applicant;
3)固定车位产权或使用权证明;
3) proof of right or right to use parking spaces;
4)关于在停车位安装电动汽车充电设备的申请(物业盖章同意);
4) application for installing electric vehicle charging equipment in parking area (approval of property seal);
5)停车位(库)平面图(或现场环境照片)。
5) parking space (garage) floor plan (or scene environment photos).
2、受理用户申请后,汽车厂商或4S店对用户资料的真实性和完整性核实无误后,会同供电公司按照约定勘查时间到现场进行用电、施工可行性勘查。
2, after accepting the user's application, the car manufacturer or 4S shop to verify the authenticity and integrity of user data, in conjunction with the power supply company in accordance with the agreed time to explore the scene to power, construction feasibility investigation.
3、供电公司负责对用户电源条件进行确认,完成《自用充电设施用电初步可行性方案》编制。
3, the power supply company is responsible for confirming the power supply of the users, and completing the preliminary feasibility plan for the use of the charging facilities for personal use.
4、汽车厂商或4S店负责对充电设施建设的施工可行性进行确认,会同供电公司于7个工作日内出具《新能源小客车购车充电条件确认书》。
4, the car manufacturer or 4S store is responsible for the construction feasibility of charging facilities to confirm, and in conjunction with the power supply company within 7 working days issued "new energy passenger car purchase charging conditions confirmation".
电动汽车充电桩安装指南
Guide for installation of electric vehicle charging piles
电动汽车充电桩安装第二步:供电方案申请
Electric vehicle charging pile installation second steps: power supply program application
用户正式签订购车合同后,可自行或委托汽车厂商或4S店向所在区域供电公司营销部(客户服务中心)提出用电报装申请。供电公司营销部(客户服务中心)在7个工作日内正式答复供电方案。用户应在有效期内到供电公司营销部(客户服务中心)办理确认手续。
After the user has formally signed the contract for purchase of the car, he or she may entrust or entrust the car manufacturer or 4S store to the power supply company in the region, and the marketing department (customer service center) puts forward the application by telegram. Power supply company marketing department (customer service center) within 7 working days, the official reply power supply program. The user shall go through the confirmation procedure at the marketing department of the power supply company (customer service center) within the period of validity.
电动汽车充电桩安装指南
Guide for installation of electric vehicle charging piles
电动汽车充电桩安装第三步:安装施工
Electric vehicle charging pile installation third steps: installation and construction
用户正式取得供电方案确认后,由汽车厂商或4S店组织开展充电设施工程建设,充电桩设备选型应符合国家相关要求,但不同车企所选择的充电设施建设企业会有所不同。不含土建工程的充电设施施工应在3个工作日内完成。
The user has been officially confirmed by the power supply scheme, automobile manufacturers or 4S shops to organize the construction of charging facilities, shall comply with the relevant national requirements for charging pile equipment selection, but different car charging facilities chosen enterprises will be different. The construction of the charging facilities without civil engineering shall be completed within 3 working days.
电动汽车充电桩安装指南
Guide for installation of electric vehicle charging piles
6
Six
电动汽车充电桩安装第四步:验收申请
Electric vehicle charging pile installation fourth steps: acceptance request
充电设施建设完成后,用户需向所在区域供电公司营销部(客户服务中心)提出验收申请。工程检验合格并办结相关手续(供用电合同签署)后,供电公司于5个工作日内完成装表接电工作。在整个过程中,电力公司不收取任何费用。
After the completion of charging facilities, users need to apply for acceptance to the regional power supply company marketing department (customer service center). After the project has been inspected and the relevant procedures have been signed (signed by the power supply contract), the power supply company shall complete the work of loading and receiving the electricity in 5 working days. Throughout the process, the power company does not charge any fees.